goal
How do I schedule 'What IF' reports to run in batch mode?

fact
Remote Request Management 7.0

fact
VigilEnt Security Agent for iSeries 5.4/7.0

fix

From the Remote Request (RRM) Menu:

  1. Select Option 10  Work With What If Analysis, press Enter.
  2. Select Option 20 What If Reports, press Enter.
  3. Select Option 1 What If Transactions By Date/Time, press Enter.
  4. Verify the value of *NO is set in the 'Run Interactively?' field and press F9.
  5. Set the desired values, ensuring that the value for 'Schedule Job?' is set to *Yes and press Enter.
  6. The IBM Add Job Schedule Entry (ADDJOBSCDE) screen will be displayed so that the job can be scheduled as normal.


Additional Information

Formerly known as NETIQKB33583