All day event created in any other language than English starts one day before

  • 7018634
  • 17-Feb-2017
  • 17-Feb-2017

Environment

Novell GroupWise 2014 R2 Support Pack 1
Novell GroupWise 2014 R2 Support Pack 1 Hot Patch 1
Novell GroupWise 2014 R2 Support Pack 1 Hot Patch 2

Situation

This works fine with English language and fails when using any other interface language.

STD:

1. Login in Webaccess in German language interface, for instance.

2. Click on Calendar folder and select any day -> in 24 hours section (all day event) create a new one. You will notice that a start date is one day earlier than what you planned to create.

Resolution

Reported to engineering.  The current workaround is to set all day events via the Windows client.  The problem is seen only in WebAccess.