Incorrect date is set on Range of Days when scheduling an app

  • 10096111
  • NOVL100460
  • 07-Jan-2005
  • 19-Feb-2005

Archived Content: This information is no longer maintained and is provided 'as is' for your convenience.

Fact

Novell ZENworks 6.5 Desktop Management - ZfD6.5

Novell Application Launcher (NAL)

Novell ZENworks Management Agent + Client

Novell ZENworks Management Agent

Symptom

Incorrect date is set on Range of Days when scheduling an app

When you set the Schedule of an application  to "None" then go back to "Range of Days" the default start date and end date are set to 12/31/69.

Dr. Watson happens if you refresh nal wile the F2 Debug NAL screen is up and running.

Cause

This was happening because the default date was being set to 12/31/69. 

Fix

Fixed in ZENworks 6.5 Desktop Management Support Pack 1 found at Novell Support